Easy, peasy!
- From this window, simply press the "Add task" button to add your Flows in the logical order
- Fill in the fields in this specific Order
- Left-side of the form
- Task name
- Task timing - Choose "Offset" if it's the first task
- After: Task starts after the reference-task is completed
- At the same time as: Task start at the same time as the reference-task
- Days offset from project start: The number of days following the start of the playbook this task should start
- Weight: Level of difficulty of this task. - We recommend using the same scale for all Flows, 0 being easy and 10 extremely hard
- Description: Short blurb describing the task
- Right-side of the form
- Chose Task Duration: The number of days end to end this Flow typically takes to be completed.
- Choose an existing Flow.
- Client Visible: Tick if you want this Flow to appear into the Mutual Action Plan.
- Left-side of the form